A new Scottish court judgment demonstrates the risks of an unsuccessful pass down: the exclusion clauses simply did not work. If you want a successful “teflon tube” pass down, you need to approach the task very carefully.

Pass down is a familiar phrase in the world of construction contracts. In the context of a PPP/PFI, project lawyers dream of a perfect pass down where the Project Co literally passes down its full obligations under the head Project Agreement to its sub-contractors, who are engaged to carry out the separate construction and operational aspects of the project.

A perfect pass down was once elegantly described to me as a “teflon tube” - nothing sticks and the direction of travel is always downwards towards the subordinate contracts. However, partial step down is arguably a much trickier affair and requires careful drafting to avoid unwelcome results. The recent Scottish case of Agilisys Limited vs. CGI IT UK Limited [2018] CSOH 26 highlights the perils of an improper pass down.

CGI was engaged by Edinburgh District Council to provide certain IT and communication services. CGI in turn sub-contracted some of these services to Agilisys. The Agilisys sub-contract attempted to pass down the provisions of the main Council contract, but it was riddled with errors and inconsistencies, referring, in part, to terms that had no relevance to services to be provided by Agilisys.

The parties fell out and Agilisys rescinded (terminated) the sub-contract for material and repudiatory breach by CGI. Sitting within the sub-contract were two exclusion clauses which if effective, would have prevented Agilisys from recovering loss of profits and business opportunities. Agilisys alleged the loss of the sub-contract caused them to lose lucrative partnering and other arrangements, while CGI firmly rejected this and mounted a defence based on the exclusion clauses.

One of the two exclusion clauses was a direct lift from the Council contract, and it had not been adapted to refer to the particular services and obligations within the sub-contract. Met with the Judge’s swift condemnation: “it is in a literal and direct sense meaningless”, that clause quickly stuck itself at the top of the teflon tube.

Undeterred, CGI argued that the remaining exclusion clause should be given a literal and strict meaning. Agilisys on the other hand argued that a literal reading would exclude CGI’s liability for claims for payment under the sub-contract: that would be commercially nonsensical, and a result that neither party could have intended.

The Court held, against the background of errors and discrepancies arising from a poor attempt at pass down, that the remaining exclusion clause lacked clarity. The correct meaning and extent of these two clauses could only be determined by leading evidence about the background to the deal.

The Agilisys case provides us with a definitive summary of the current approach to contract interpretation but, perhaps more importantly, it serves as a reminder that if you want a teflon tube, you need to approach it carefully, using the correct materials and devoting sufficient time to construct it properly.

Written by

Related News, Insights & Events

Error.

No results.

Health And Safety Statistics 2026

Health and Safety Statistics 2026: What they mean for energy, construction and other high-hazard industries

19/11/2026

This blog discusses the latest health and safety statistics and what they mean for organisations operating in high-hazard industries

Read more
Construction & Projects Winter Seminar It's All About The Money Website

Construction & Projects Winter Seminar: It's All About The Money

19/11/2026


Join us for an in-person seminar as we explore the latest developments in insolvency, retention reform and payment practices and discuss practical steps businesses can take to protect their outcomes.

Read more
Why Payment Notice Deadlines Matter In Construction

The smash and grab lives on: why payment notice deadlines matter in construction

13/11/2026

Thirty years on, courts still apply Construction Act payment deadlines strictly. A notice served one day late is out of time, however sound the claim.

Read more

Want to hear more from us?

Subscribe here Subscribe here