Scotland’s COVID-19 vaccinations are underway and will be delivered faster through mass vaccination centres.

4.5 million adults in Scotland need to be vaccinated over the next 6 months or so.

The arithmetic shows that the Government’s target needs to be 400,000 vaccinations every week, in order that we can all get our two doses. This target should be achievable once more large vaccination centres come on stream.

Since November 2020 the Construction and Projects team here at Burness Paull has been working hard on providing legal support in connection with setting up of a number of large vaccination centres in the Lothians.

Sites include Queen Margaret University near Musselburgh, and Pyramids Business Park in West Lothian. Various other locations are being added to the project too.

Ordinarily, such a project to provide health related accommodation and deliver services from it, would be split into a number of phases.

Firstly there would be site and infrastructure decisions, secondly the planning and structuring phase, and then the phases of procurement/construction, all before the operational phases. Each phase would take and last for many months.

However, a global coronavirus pandemic is an emergency, requiring a very different approach.

Thankfully, the procurement rules do envisage such emergencies, which permitted NHS Lothian to engage with its framework partner SE hub almost immediately when the need for such vaccine centres was known. They in turn were able to bring to the table their key supply chain members with whom good relationships existed.

To maintain the programme, within two days of appointment we had agreed a contractual letter of intent, which permitted the ordering of key temporary infrastructure which is to be deployed at the various sites.

We then had to negotiate and agree terms for the design and construction of the facilities, which dealt such matters as the property, insurance and consenting.

Of importance to all parties was the pricing, which it was agreed required to be on a cost reimbursable open book basis, with appropriate audit arrangements.

It was also important to include provisions to ensure proper performance, ultimately fenced by termination provisions. The contract for this element was signed early January and the first site comes on stream from the start of February, with the others to follow shortly thereafter.

Since then we have been working on the Facilities Management (FM) arrangements, which will be important to ensure the smooth running of the sites.

Each site will be operating at least 12 hours a day. These will include planned services such cleaning, security, porterage, traffic management, and reactive services such as ad hoc repairs.

Again, parties are adopting a pragmatic approach to agreeing what is required, and what happens if services are not delivered to the required quality to enable the centres to operate as intended.

From our legal perspective, we just could not adopt a cookie–cutter approach to what was required here. Rather drawing on past experiences of contracting for temporary accommodation and FM arrangements, and working collaboratively, we had to innovate, which is always good.

We are benefitting at this time from the feel-good factor of working on such an important and worthwhile project. We are also taking our place in the queue to receive our own jabs hoping that will not be too far away now.

Chris Mackay, Partner, and Chris Horsley, Director, are both construction and project lawyers with lead roles in Burness Paull’s Healthcare and Life Sciences Group
Chris Mackay

Chris Mackay

Consultant

Construction


Chris is a consultant in the firm's Construction and Projects team. Chris specialises in contentious construction law and is a recognised expert in this field.

Get in touch
Chris Horsley

Chris Horsley

Director

Construction


Chris specialises in projects, energy and commercial contracts and advises both public and private sector clients in relation to major projects.

Get in touch

Related News, Insights & Events

Health Trends In 2025 (1)

Health Trends in 2025: What we’ve seen and what’s to come

As we enter Q2 of 2025, what are some of the key trends across life sciences and health and care that we’ve seen so far, and we think are likely to play out over the remainder of the year?

Read more
Expansion Of Right To Work Checks What You Need To Know

Expansion of Right to Work checks: What you need to know

This blog discusses the UK government's tougher stance on immigration compliance, particularly around right to work checks.

Read more
Courts Provide Guidance On “Reasonability” In Compensation On Termination Recovery

Courts provide guidance on “reasonability” in compensation on termination recovery

A new decision from the Privy Council has provided some guidance on the limits of provisions around the recovery of supply chain costs upon termination for convenience or employer default.

Read more

Want to hear more from us?

Subscribe here