The Scottish Appeal Court has confirmed that the standard NEC dispute resolution provision, which provides for disputes to be decided firstly by adjudication, and then by a specified tribunal, does not deprive parties of their fundamental right of access to the court.

However the principle of compulsory adjudication on the merits of a dispute does give rise to a number of issues. These include the potential need to undertake multiple adjudications before the court can consider the merits as a whole, with the very uncertain timescales that involves. There is also the question of the extent to which the clause W2 might be argued to affect interim remedies e.g. interim interdict. We will consider these points further.

The case of Fraserburgh Harbour Commissioners v McLauglin & Harvey Limited is of particular interest because it affects the interpretation of the standard NEC dispute resolution provision which is used in most NEC contracts in the UK. Further, the case has wider implications in Scotland in circumstances where alternative dispute resolution is specified under the contract.

In this case, the pursuer and the defender had entered into an NEC3 Engineering and Construction Contract for harbour deepening works.  The contract included clause W2 which essentially provided that disputes should be resolved firstly by way of adjudication and then by way of arbitration (although in many other contracts the tribunal will be specified as the court).

The pursuer raised court proceedings for damages in respect of certain defects in the works for the primary purpose of interrupting prescription (i.e. time bar) prior to any adjudication proceedings being commenced.  There was no dispute between the parties that the defender was entitled to insist on its contractual right to have the merits of the matter determined by adjudication, and then arbitration, rather than the courts.  However, the parties were in dispute as to what should happen to the court proceedings in the meantime: should they be sisted (i.e. paused) or dismissed?

First Instance Decision

At first instance the Court had decided that clause W2 acted as a contractual bar prohibiting the raising of court proceedings.  Accordingly, the court decided that the action should be dismissed instead of being sisted pending resolution of the dispute by adjudication and then arbitration.

Appeal Decision

The appeal court disagreed with the approach of the Court at first instance and decided to sist the court proceedings. This was because the decision to dismiss the court proceedings was at odds with both:

  • “the well-known and established principles” relating to alternative dispute resolution clauses; and
  • Section 10 of the Arbitration (Scotland) Act 2010 which expressly provides that the Court must sist court proceedings where there is an arbitration agreement covering that matter.

The Appeal Court referred to the leading case from 1894 which clearly confirms that clauses for alternative dispute resolution do not generally completely exclude the jurisdiction of the Court and that the proper course for the Court to take is to “stay procedure until it has been settled by arbitration”.  As the Appeal Court said, the reason for this rule is not too difficult to understand: the right of access to the courts is the most basic of principles. As such, “a contract will not be interpreted as excluding the Court’s jurisdiction unless by clear words or necessary implication”.

The wording of clause W2 in the present case did not go any further than stating that adjudication, and a subsequent notice of dissatisfaction, were necessary before proceeding to arbitration.  Clause W2 did not seek to attempt to deprive the pursuers of their right to raise court proceedings. In fact, clause W2 (in this instance) did not refer to the Court at all.  As such, raising a court action prior to adjudication did not breach its terms.

The Court, of course, would not engage with the merits of the dispute unless the agreed method of ADR failed to resolve the dispute. Otherwise, the Court’s competence to hear the case was not affected and accordingly “the procedure to be followed is to sist the cause meantime”. Accordingly, the Court’s door remains firmly open for an action to interrupt prescription or for other interim remedies such as interdict or diligence on the dependence.

Further, Section 10 of the Arbitration (Scotland) Act 2010 provides that, on an application by a party to legal proceedings concerning any matter under dispute, the court “must” sist those proceedings, if there is an arbitration agreement covering that matter. Since there was such an arbitration agreement in this case then the Court was clearly required to sist the action.

Points for consideration

  1. Whether compulsory adjudication prior to court or arbitration makes sense in all scenarios is questionable.  Adjudications require to deal with single disputes. It may take a good number of adjudications before either party could, where clause W2 applies, have the benefit of the court or an arbitrator, considering the wider dispute. It is quite possible to delete the provision by means of a Z clause. Either party can still adjudicate at any time, but the door of the court or arbitrator remains open where appropriate.
  2. Where clause W2 is to be included in a contract then it would make sense to clarify that the provision will not prevent either party seeking to seek interim remedies e.g. interim interdict, diligence on the dependence, or to commence proceedings for purposes other than immediate determination of the merits e.g. to avoid time bar.
  3. The case in question specified the tribunal as “arbitration”.  It is an open and, as yet unresolved, question as to whether the Court’s decision would have been different if the tribunal had instead being specified as “court”.  In that case, there would be express wording referring to the Court and parties may seek to argue that this wording is sufficient to exclude the jurisdiction of the Court until after adjudication proceedings have been concluded and notices of dissatisfaction issued.  Our understating is that we won’t have to wait long until we have an answer from the Court on this point.
  4. The Court, in deciding that two first instance decisions from England and Wales were not in point, highlighted that considerable care would have to be taken before applying them to procedure in the Scottish Courts.

Returning to the question posed the answer is yes the courts’ doors are generally open to allow proceedings to be raised, with the merits being determined by ADR, unless parties agree otherwise.

Written by

Chris Mackay

Chris Mackay

Consultant

Construction

chris.mackay@burnesspaull.com +44 (0)131 473 6151

Get in touch

Related News, Insights & Events

Building Safety In Scotland Legislation Comes Into Force On 6 January 2025

Building safety in Scotland: Legislation comes into force on 6 January 2025

The Act was introduced by the Scottish Government to reduce the risk to life from unsafe cladding on high-rise homes.

Read more
LOI Website

Letters of Intent in construction projects: Practical insights

Letters of intent (LOI) are widely used in the construction industry. Here we explore what LOIs are, their role in the industry and how they can be used effectively.

Read more
Scott Duncan 73108362 Small

Burness Paull strengthens energy and infrastructure expertise with appointment of new partner

03/12/2024

Burness Paull has strengthened its offering for clients in the energy and infrastructure sectors with the appointment of Scott Duncan.

Read more

Want to hear more from us?

Subscribe here