Chris Mackay considers a recent court judgment about the NEC contract and asks: can a client be a Project Manager?
NEC allocates duties to the Project Manager (PM) which include agency duties on behalf of the Employer (e.g. giving instructions to vary the works), and decision making functions (e.g. deciding the date of Completion). In performing his, or her, decision making function the PM is required to act in a manner which has variously been described as independent, impartial, fair and honest.
Can the Client appoint himself as PM? Yes – but timing is critical.
If a direct employee of the Client is appointed and his details are completed in Contract Data Part 1 (see the worked example in the new NEC 4 guidance), the fact that the PM is a Client employee is then known to the Contactor at the outset. It is implicit that the Contractor is agreeing to this.
However, what happens if a third party is appointed as the Project Manager and the Client mid-contract elects to replace that third party PM? Clause 14.4 of NEC4 says that the Client may replace the Project Manager after notifying the Contractor of the name of the replacement. But what if the replacement is its own direct employee? The answer is rather different. It was recently held in ICI V Merit Merril Technology Ltd that an express term of contract would be required to permit such a material change to occur.
The backdrop to the change of PM in the ICI case was that the third party appointed PM was given an instruction by ICI that any revisions in the PM’s assessments of the effect of numerous PMIs needed to be signed off by ICI prior to inclusion in the certification. The PM, entirely correctly, identified that he was no longer empowered to carry out his responsibilities in terms of the contract and had no option but to resign. This led on to ICI purportedly appointing its own employee as the replacement PM. The court said that this appointment was a breach of contract and ineffective.
So what lessons do we learn from ICI?
- If a Client wishes to reserve the right to replace a third party PM during the project with a direct employee PM, then it should include an express right to do so, by means of a Z clause.
- Clients should consider carefully the wisdom of having direct employees perform the PM role. Does the employee have experience of that type of role and the capacity to resource the role effectively? Does the individual have the authority to exercise the powers under the contract in an impartial manner?
- Contractors should consider, and potentially enquire, why a Client has not elected to appoint a third party PM; and
- Third party PMs must not forget that, in exercising any decision making, they must do so in an impartial, fair and honest way, not bound to the Client’s instruction.
Written by
Related News, Insights & Events
Error.
No results.
Countdown to a retention ban: the UK Government takes the next step
22/06/2026
Here we discuss the proposed UK ban on retentions under the Small Business Protections Bill, its scope, timing, and the practical impact on construction contracts and security arrangements.
Reflections on BCO 2026: flexible offices and a shift to partnership led leasing
18/06/2026
Here, we reflect on some of the key themes emerging from the British Council for Offices conference 2026, including more flexible workplaces and partnership led leasing models
Scotland’s build-to-rent reset: regulatory clarity restoring investor confidence
17/06/2026
Here, we examine Scotland’s build to rent recovery as clearer regulation removes uncertainty, attracts investors, and shifts momentum toward single family schemes despite viability pressures.
{name}
{properties.pageSummary}
{properties.headline}
{properties.pageDate|date:dd/MM/yyyy}
{properties.shortDescription}