The ongoing squeeze on construction material supplies has been headline news in the industry.

My colleague Kathleen McAnea wrote about potential solutions earlier this summer in Construction materials shortage – blip or blunder?

On 28 July 2021, the Scottish Government responded to the situation by issuing guidance - Resources for construction projects: CPN 3/2021 - setting out suggested measures which contracting authorities may take in order to try to manage and mitigate the current market pressures on resources.

Projects currently on or about to proceed to site

The guidance recognises that there are differences in the challenges posed in relation to projects which are currently in procurement and those which are either already on site, or very close to being so.

Where contracts have already been agreed, the parties are bound by those agreed terms, so the focus must be on resolving difficulties by prudent ongoing contract and relationship management.

Given that focus, the main suggestions which the guidance offers revolve around:

  1. the review and examination of the contract terms and the evidence available to support the impact on the project; and
  2. honest and open discussions with contractors about mitigation.

On the one hand, it recommends the taking of legal advice so the contracting authority is fully aware of its contractual rights.

On the other hand, it also suggests the most effective solutions are likely to be found in working closely with contractors to identify how risks to the delivery of projects might be best mitigated.

It is a balancing act between knowing your rights and accepting that a negotiated solution might be more effective in achieving a positive outcome.

Projects in development

Where contracts have not yet been fully agreed, the guidance recommends that contracting authorities carry out an urgent review of project feasibility and commercial viability.

If this review identifies material issues, contracting authorities are advised to reconsider whether some projects should proceed to market at this time. It is generally thought that the current market disruption will have dissipated by Q1 2022.

Once again, open discussion is recommended as the way to produce better outcomes. The key is to make sure that these discussions have taken place before the contract has been signed.

In terms of drafting proposals, the addition of price fluctuation clauses into tender documents and contracts is suggested, as opposed to strict adherence to the typical public sector stance of requiring fixed price tendering.

Price fluctuation clauses have been around for many years, but were rarely used in practice. Will we now see a change?

Careful drafting is required to achieve the desired effect of reducing the base tender price, while putting in place reliable ongoing assessment measures to track the actual costs incurred during project implementation.

Collaboration

The essence of the guidance is collaboration.

The strong recommendation is that contractors should not be required to shoulder an unreasonable allocation of risk in relation to the current volatility, and that value for money can be achieved for the contracting authority whilst appropriately recognising a valid situation in the market.

This has been a consistent message of recent Scottish Government guidance. It echoes the tone of the Government’s COVID-19 advice to contracting authorities.

Interestingly, we have not seen that guidance resulting in a consistent approach to COVID-19 relief, with public sector bodies providing a range of differing levels of relief to their contractors.

What now?

Our expectations are that strategies will continue to vary on a case-by-case basis.

In practice, we have recently seen a wide range of positions adopted by contracting authorities. These have included programme extensions; and advance materials procurement by contractors which is underwritten by the client.

It is important to consider the legal implications of any steps taken to deal with the materials shortage. The best of intentions can, from a legal point of view, lead to unintended consequences.

Having said that, there is no doubt that collaboration based on the mutual appreciation of a risk - which is neither party’s fault - would seem to be a pragmatic approach.

If you would like to discuss this guidance and your options, please do not hesitate to get in touch.

Written by

Related News, Insights & Events

Building Safety Levy (Scotland) Bill Introduced

Building Safety Levy (Scotland) Bill introduced

Introduced on 5 June 2025, the Building Safety Levy (Scotland) Bill proposes a new tax which, if passed, will be known as the Scottish Building Safety Levy ("the Levy"). 

Read more
Performance Security Part 2

Performance security part two: Parent company guarantees

We are considering recent trends and what these mean in practice. Part 1 considered performance bonds; here we’ll focus on parent company guarantees (PCGs).

Read more
Performance Security Part One Performance Bonds

Performance Security Part One: Performance Bonds

Performance security is a topic often put to the bottom of the list in construction contract negotiations but is an important consideration for clients and contractors before commencing a project.

Read more

Want to hear more from us?

Subscribe here Subscribe here