The standard NEC dispute resolution provision which provides for disputes to be decided firstly by adjudication and then by a specified tribunal have been under closescrutiny by the Scottish appeal court in the case of The Fraserburgh Harbour Commissioners v McLaughlin & Harvey Limited, [2021] CSIH 58.

The pursuer raised court proceedings for damages in respect of certain defects in the works for the primary purpose of interrupting prescription (i.e. time bar) prior to any adjudication proceedings being commenced.  There was no dispute between the parties that the defender was entitled to insist on its contractual right to have the merits of the matter determined by adjudication, and then arbitration, rather than the courts.  However, the parties were in dispute as to what should happen to the court proceedings in the meantime: should they be sisted (i.e. paused) or dismissed?

You can read Chris Mackay and Andrew Little’s blog to find out why the court concluded it would sist the current court action pending the outcome of an adjudication and arbitration determining the merits of the dispute.

Related News, Insights & Events

Error.

No results.

Case Update The Importance Of Clear Drafting In Collateral Warranties And Time Bar

Case Update: The importance of clear drafting in collateral warranties and time bar

04/02/2026

Here, we discuss a Court of Session appeal confirming there is no presumed time bar in collateral warranties, with courts focusing strictly on the wording agreed and not implying defences.

Read more
Heat On Date For Heat Networks Regulations What Operators And Owners Need To Know

“Heat on” date for Heat Networks Regulations – what operators and owners need to know

27/01/2026

In this article, we explain the new Heat Networks Regulations, Ofgem’s role, authorisation requirements and what operators and developers need to do now.

Read more
Supreme Court Overturns Court Of Appeal On Termination For Repeated Default Under JCT Contract

Supreme Court overturns Court of Appeal on termination for repeated default under JCT contract

22/01/2026

In this article, we consider the Supreme Court’s decision overturning the Court of Appeal on contractor termination rights under clause 8.9 of the JCT Design and Build Contract.

Read more

Want to hear more from us?

Subscribe here Subscribe here